    SMU found lead times essentially remaining the same on hot rolled (negligible change from 4.0 weeks to 3.97 weeks) and galvanized (6.0 weeks vs. prior 6.07 weeks). Cold rolled lead times dropped from 6.2 weeks to 6.06 weeks while Galvalume lead times moved out slightly from 6.55 weeks to 6.80 weeks.

     