Steel Mills

January 28, 2014
US Steel Wants to Build EAF at Fairfield
Written by John Packard
Mario Longhi, CEO of U.S. Steel announced to those on the US Steel conference call that the company has started the process of replacing the existing blast furnace at the Fairfield, Alabama facility with a brand new electric arc furnace (EAF).
During the call, Mr. Longhi advised that the expect the permitting process to take 9-12 months. If approved, the expect construction could begin by the 3rd Quarter 2015 and would be completed by mid-2017.