SMU Data and Models

February 23, 2014
Hot Rolled Lead Times Slip – Others Rally
Written by John Packard
Domestic mill lead times hardly budged according to our most recent SMU steel market survey of the flat rolled steel market. Those participating in our survey put the average hot rolled lead time at 3.70 weeks. This is down slightly from the 3.89 weeks measured at the beginning of the month. The three month moving average for HR lead times is 4.12 weeks.
All of the other products – cold rolled, galvanized and Galvalume actually saw increases in their lead times compared to the beginning of February.