    Mill Lead Times Slip

    Written by John Packard


    According to the results of our latest flat rolled steel market survey just completed earlier today, mill lead times are slowly beginning to move in (get shorter) on almost all products followed by Steel Market Update.

    Our respondents reported shorter lead times on hot rolled which were at 4.91 weeks on the 15th of May and are now being reported as averaging 4.52 weeks. However, the latest HRC lead times are still further extended than the 3.38 weeks reported at this time last year.