June 14, 2015
Big River Steel Construction Update
Written by Sandy Williams
The $1.3 billion Big River Steel mill, in Osceola, Ark., is beginning to take shape. The site excavation, totaling 1,178,000 cubic yard, is nearly 100 percent complete, said Mark Bula, Chief Commercial Office in a progress report to Steel Market Update.
About 26 percent of the 235,000 cubic yards of concrete that will be needed during construction has been poured for the scrap pits, zinc pot basement, holding area and caster basement.