    Steel Mill Lead Times Beginning to Move but Still Below Year Ago Levels

    Written by John Packard


    Flat rolled steel lead times, according to those responding to this week’s market analysis questionnaire, have begun to move. The question now becomes will they continue to move and will they move out far enough to force buyers back into the market?

    Our respondents reported hot rolled lead times as having extended slightly from the 3.05 weeks reported at the beginning of December to 3.32 weeks this week. Over the past 3 months lead times have been averaging less than 3.0 weeks. One year ago HRC lead times were reported to be averaging 3.53 weeks.