    ArcelorMittal Coke Battery Repairs on Track

    Written by Tim Triplett


    ArcelorMittal’s $19.25 million project to repair its No. 2 coke battery at Burns Harbor is on track to meet its 2022 completion date, reports the company.

    The coke battery’s last rebuild was in 1994. Work on the five-year project began last year. The company continues to produce coke at the facility, which has two six-meter coke batteries, as it works on three ovens at a time, primarily replacing brickwork in the roofs. So far, 18 of No. 2’s 82 ovens have been repaired. The batteries are designed to produce about 950,000 tons of coke per year to supply Burns Harbor’s two blast furnaces.

    Latest in Steel Mills