Flooding Shuts Down All Furnaces at U.S. Steel Gary Works
Written by Sandy Williams
A water pipe break at U.S. Steel Gary Works has resulted in the shutdown of all furnaces at the facility due to safety concerns.
Said U.S. Steel spokeswoman Amanda Malkowski, “On November 27, U.S. Steel reported a service water leak that caused flooding at our Gary Works facility near our blast furnace operations. As a precaution, we proactively stopped the blast furnaces and steel production to protect our people, assets and the environment until the issue was resolved. The water disruption has been resolved and the team is in the process of restarting auxiliary assets within Gary. We expect the first blast furnace to be brought back on line over the weekend. Gary Works is expected to be back to its pre-flood blast furnace footprint by mid-week. Customers should not be adversely impacted by these steps.